Client: | Holcim Australia |
---|---|
Duration: | 3 months |
Industries: |
|
Services: |
|
Context: | As part of Holcim’s electrical safety management system, they require periodic electrical safety audits of their plants. Based on the findings of the audits, arc flash studies were recommended to determine and mitigate the arc flash hazard level present at the switchboards on site. |
Our Role: | Engenuity currently conducts electrical safety audits for Holcim’s plants across Australia. Engenuity identified an opportunity for improvement during these audits by determining the arc flash hazard level on site. Holcim engaged Engenuity to complete these arc flash studies. |
Key Outcomes: | The arc flash studies provided Holcim with precise information about the arc flash hazard level present at their plant’s switchboards, the PPE requirements to safely operate the switchboards and potential mitigation methods to improve safety on site. |
Client: | Holcim Australia |
---|---|
Duration: | 4 years |
Industries: |
|
Services: |
|
Context: | Holcim Australia has mandated periodic external audits of electrical assets across a range of plants to verify electrical safety. |
Our Role: | Engenuity were appointed to assess hazards and verify safety management system compliance in electrical safety. Engenuity completed the audits across quarries, precast facilities, concrete & manufacturing plants and mobile batch plants. |
Key Outcomes: | Engenuity, in consultation with Holcim, has identified particular focus areas for improvement. Electrical audit reports were provided for each inspected plant, detailing the safety risks and equipment condition accompanied by corrective actions and timelines. |